Project Manager
Dan Gilson

907.834.5040
PO Box 3089
Valdez, AK 99686

 

Prince William Sound Response Rate Analysis


Response Rate The council commissioned a report to better understand how encounter rates affected the recovery rate capabilities of the Nearshore and Open Water oil spill response in Prince William Sound.  As the principle methodology, this study utilized an ASTM F1780 Standard that considers actual encounter rates rather than the EDRC approach which focuses on de-rated efficiencies for skimmers.  The analysis in this study included understanding the recovery rates based on an instantaneous spill and a continuous spill.

 

 

 

 

 

 

 

 


Prince William Sound Recovery Rate Analysis. October 27, 2008 Prepared by Censum Northwest, LLC P.O. Box 12082 Olympia, WA 98508 www.censumnw.com

Return to Alphabetical List of Projects